Walk east on Bellevue Avenue toward Hermitage Road this month and the sidewalk gives way, for about a quarter mile, to a strip of packed gravel running parallel to the street. Half of it is already paved. Trucks show up most weekday mornings. Nobody has put up a sign explaining what it is, but anyone who has followed the Fall Line Trail's slow crawl through Richmond for the past two years already knows: this is where Richmond's own stretch of the trail begins, and it is finishing closer to Bellevue's own front door than most residents realize.
The Bellevue Civic Association describes the neighborhood as adjacent to the 262-acre Joseph Bryan Park, and for most of the past century that has meant one thing: a place to walk to. What's different this month is that the park's newest mile of paved path is being measured against Bellevue's own street grid, not just the park's internal geography. According to the Friends of the Fall Line's July 2026 update, the gravel base for this segment already extends nearly to Bellevue Avenue and beyond the park's soccer fields, with roughly half to sixty percent of that base now paved. The project is on schedule to finish paving on August 21, 2026.
The Segment That Took Two Years to Approve
This particular mile has a longer paper trail than most park improvements ever get. The city broke ground on it in August 2024, the first Richmond trailhead of the Fall Line Trail's eventual 43-mile run from Ashland to Petersburg. What followed was not a quiet construction schedule but a genuine neighborhood argument. Richmond's Urban Design Committee and Planning Commission approved the route in June 2024, but pushback from park patrons over tree removal kept the design under review through most of 2025.
The numbers from that fight are worth knowing, because they explain why the trail looks the way it does today. An engineering report submitted to the city put the approved route's cost at $2.3 million, affecting only six trees. Two alternate routes that would have wrapped around more of the park's perimeter were rejected specifically because they would have cost between $3.4 million and $4.1 million and removed more than 40 trees. More than 200 people showed up to a city hearing on the plan in April 2025, many arriving as part of a group bike ride organized by the local nonprofit Sports Backers.
Here's the timeline in plain terms:
| Date | What happened |
|---|---|
| August 2024 | Groundbreaking at Bryan Park, Richmond's first Fall Line Trail segment |
| June 2024 | Urban Design Committee and Planning Commission approve the route |
| April 2025 | Over 200 residents attend a public hearing on the final design |
| July 2026 | Gravel base reaches nearly to Bellevue Avenue, 50 to 60 percent paved |
| August 21, 2026 | Scheduled completion of paving |
No ribbon cutting date has been set yet. That detail matters if you're the type of resident who plans a Saturday around a grand opening. The pavement will be finished before the ceremony is.
What Finishes This Month Is Not What You Think
Here is where the story locals tell each other starts to drift from what's actually true. The framing around the Fall Line Trail has always been regional: a continuous path connecting Ashland to Petersburg, with Bryan Park as one stop along the way. That framing suggests Bellevue's new mile of pavement is the beginning of a bike commute north out of the neighborhood.
It isn't, at least not yet. As of late 2025, only two stretches of the 43-mile trail were fully open to the public: a 4.8-mile segment connecting the Ashland Trolley Line to Woodman Road in Henrico, opened in September 2025, and a short connector already linking Henrico's Spring Park to Bryan Park, open since July 2024. What's missing is the corridor between them. Henrico's own segment is planned to run 7.5 miles from Bryan Park Avenue to the Chickahominy River at the Hanover County line, and as of this summer it remains mostly in design. The northernmost mile of it, a stretch through Villa Park, only just got a construction contract awarded to Sagres Construction, and the section further out toward Longdale is not even scheduled for a construction bid until the fourth quarter of 2026.
In other words, the piece of trail finishing at Bellevue's edge this month sits at the Richmond end of a chain whose middle links are still years from being built. You will be able to ride the trail through Bryan Park itself, and even a short distance north to Spring Park. You will not be able to ride it all the way to Ashland, because the seven and a half miles that would close that gap are still mostly on paper in a Henrico County planning office.
The mile finishing this month ends the trail. It doesn't start one.
That distinction matters for anyone deciding whether this is a reason to buy a bike this fall or wait a few more years. The regional dream is real, and the state has committed significant funding to it, but the timeline for actually riding from Bellevue to Ashland without touching a car is still measured in years, not months.
What Actually Changes Inside the Park
The more immediate and less publicized benefit has nothing to do with Ashland. Right now, families using Bryan Park's playground, disc golf course, and soccer fields share internal park roadways with vehicle traffic to get between them. The city's own project description for this segment notes that the new path is meant to give park users, particularly families with children, an off-road route between those amenities and the newer restroom facility near Shelter 1.
That's a small thing on paper and a real one in practice if you've ever walked a stroller past a parked car near the soccer fields on a Saturday morning. The trail finishing this month solves an internal circulation problem inside a park Bellevue residents already use every week, whether or not it ever links up to Henrico's unfinished middle section.
The Saturday Rhythm Doesn't Wait for Ribbon Cuttings
None of this changes what's already working in Bryan Park. The RVA Big Market runs every Saturday at 4308 Hermitage Road, with summer hours from 8 a.m. to noon through October before shifting to a 9 a.m. to noon winter schedule. It's one of the reasons the alternate, tree-heavy trail routes got rejected in the first place: city planners flagged concerns that a perimeter route could disrupt the market's footprint, which runs on the same gravel and grass the trail now crosses.
Regulars know the market by its vendors more than its hours. Owl Spoon and Fourteen Acres show up most weeks. Parousia Coffee and Sweet Jane's Kitchen have both become the kind of stall people plan their walk around. None of that changes when the pavement finishes on August 21.
The rest of the park runs on its own separate calendar. The 18-hole disc golf course, rated 4.3 out of 5 by more than 3,600 reviewers on UDisc, has a Basket Bashers Virginia Amateur Tour Finale scheduled for September 1. Dogs are welcome on leash throughout most of the park, but not inside the Azalea Garden itself. For off-leash time, the separate Northside Dog Park remains the option, not Bryan Park proper.
None of these rhythms are new. What's new is that for the first time, getting between them inside the park won't mean sharing a road with a car.
What This Means If You're Watching the Neighborhood
If you live in Bellevue, the practical takeaway is narrow but useful: expect the pavement near your own street to be finished by late August, expect no fanfare around it for a while, and don't plan a bike trip to Ashland based on this milestone. The regional trail is a real, funded, multi-year project, and Bellevue happens to sit at one of its more advanced endpoints. The gap that would make the whole thing usable end to end is in Henrico's hands now, not Richmond's.
For anyone who has watched Bellevue's mix of Foursquares, Tudor Revivals, and bungalows fill in over the past few years, this kind of infrastructure detail is part of what makes the neighborhood worth tracking closely, not just as a place to live but as a place that keeps adding small, verifiable reasons to stay. If you're weighing a move into Bellevue, or you already live here and are curious what a home in this market actually looks like right now, Option 1 Realty knows this stretch of Richmond's Northside street by street, and can walk you through what's changing in the neighborhood alongside what a sale or purchase here would actually look like.